Construction New
Education Building
May 2008 - Present
(Updated Weekly - If There Is Progress)

Building Committee Chairman Leon Armour - Construction Foreman Dan Noma

Ground Breaking Sunday February 17, 2009
May 30, 2008 - Krafters Building Temporary Relocation
September 3, 2008 - Basement Digging
September 9, 2008 - Basement Basically Dug - LOTS OF DIRT!!!
September 15 - Basement Done - Dan's Happy!!!
September 24 - Basement Floor Poured - Wall Forms Being Placed
September 30 - Forms Almost Done - Elevator Shaft Placed - Dirt Being Removed
October 1, 2008 - Wall/Stairwell Pouring - Dirt Collapse
October 6, 2008 - East/South/West Basement Walls Poured - North Wall Setup
October 8, 2008 - North Wall Pour - NW Corner Problem Area - Dirt Use - Cleaning
Founding Pastor Marshall Lindsay (Nancy) Visit October 11, 2008
October16/17 - Installing 1st Floor Beams and Floor Support Fictures
October 21 - Installing Slats - "Acrobats? at Work - Flooring Ready
October 24, 2008 - 1st Floor Layed - Setting Up for 2nd Floor
October 28, 2008 - 1st Floor Walls Going Up - Dirt Replacement
October 31, 2008 - Dirt basically Gone - 1st Floor Walls Almost Complete
November 4, 2008 1st Floor Framing - Stairs - 2nd Floor Walls Progress
November 10, 2008 East/North Ends and Openings - Roof Blocks Installing
November 12, 2008 North Parking Lot/Columbrium Walk Through
November 20, 2008 Roof Frames Installed
November 24, 2008 Basic Roof Completed
December 3, 2008 Columbarium Views - East Parking Area Dirt/Trench
December 6, 2008 Walks Being Installed - Parking Area Filled
December 22, 2008 Roof Tiles Loaded - 1st Floor Insdie Scenes
January 16, 2009 Outside Basically Finished - "Fund Raiser " 1/23/2009
January 22, 2009 Outside/Inside Shots
January 23, 2009 "Sunday School Fund Raiser" Jan 23, 2009
March 2, 2009 "Miscelleanous Scenes"
March 2,2009 "Lower Level"
Consecration Service Sunday, March 8, 2009